Goregaon-Mulund Link Road: 2026 Progress Report

Flyovers rise, tunnel boring machines roar to life on Mumbai's most-watched infrastructure corridor.

Enquire Now

GMLR 2026: Where Flyover Construction and Tunnel Boring Stand Today

The Goregaon-Mulund Link Road (GMLR) remains one of Mumbai's most closely tracked infrastructure projects, and 2026 has turned out to be a pivotal year for both its above-ground flyovers and underground tunnels. The Goregaon Mulund Link Road is one of Mumbai's most ambitious infrastructure projects, with a 12.2-km, Rs 14,000 crore corridor of tunnels, flyovers and interchanges that promises to finally bridge the gap between the city's western and eastern suburbs. For residents and homebuyers along this corridor, every milestone here directly translates into shorter commutes and rising property interest.

Right now, the daily commute pain point is well known. Traveling from Goregaon to Mulund during peak hours can take up to 90 minutes, and once the GMLR is ready, the journey is expected to shrink to just 25 minutes. That 65-minute saving is the single biggest reason this project is watched so closely by both commuters and real estate buyers in the central suburbs.

On the flyover front, progress has been uneven. The BMC imposed a penalty of over Rs 2.09 crore on contractor S P Singla for significant delays in Phase 3 of the GMLR, with the six-lane flyover on the Goregaon side, initially set for completion in July 2025, now expected to open only in May 2026, while on the Mulund end only one arm of the six-lane flyover was set to become operational on May 31, 2026, with the remaining sections requiring additional months of work. By March 2026, an independent progress report indicated nearly 48 per cent of the flyover work has been completed, while tunnel excavation has reached 18 per cent, underscoring that the flyover package is now closer to completion than the tunnel package.

The tunnel-boring story has picked up real momentum this year. The process of lowering components of the Tunnel Boring Machine into the shaft for the twin tunnels under Phase 3-B began formally on March 11, 2026 at the Dadasaheb Phalke Chitranagari area, three months ahead of the scheduled timeline. This is being executed with genuinely heavy engineering: assembly has begun on two 14.42m-diameter TBMs for the GMLR project, marking a key milestone for what will be India's largest TBM deployment to date, with the machines set to excavate twin road tunnels beneath Sanjay Gandhi National Park, each driven in a single pass of approximately 5.3km. These are not ordinary conditions either — the machines are designed for challenging ground conditions and will operate through Deccan basalt and breccia formations at depths of up to 143m, with anticipated high groundwater pressures.

Officials have now put a firmer date on the tunnel package. Authorities are targeting the start of excavation work on both tunnels as per schedule, with tunnelling expected to be completed by October 2028 and the entire GMLR project slated for completion by December 2028. This is a meaningfully later timeline than the original 2026 target set when the project broke ground, reflecting the complexity of boring twin tunnels under a national park.

For homebuyers, the corridor's slow-but-visible progress is already shaping real estate decisions. Property advisors tracking the belt note that infrastructure-driven appreciation in Mumbai follows a well-documented pattern where prices move when projects break ground, accelerate when timelines become visible, and consolidate after completion, with Goregaon West average property rates currently sitting around Rs 32,000 per sq ft. Mahindra Lifespaces has itself flagged this corridor's importance in recent project launches — its Kanjur development is positioned with strong connectivity to the Eastern Express Highway, the Jogeshwari–Vikhroli Link Road, and upcoming infrastructure including the Goregaon–Mulund Link Road and an east–west connecting flyover in Bhandup. The developer has also secured a foothold further along the corridor, having emerged as the preferred developer for the redevelopment of a premium housing society in Mulund West, Mumbai, a project whose site sits barely a kilometre from the GMLR alignment.

For anyone evaluating a home purchase near Goregaon, Film City, Bhandup or Mulund, the practical takeaway is this: the flyover phase should ease local traffic through 2026-27, but the real east-west shortcut only arrives once the twin tunnels open, now targeted for late 2028. Buyers with a 3-4 year investment horizon are the ones best positioned to capture the full connectivity upside this project promises.

GMLR 2026 Update: Tunnel Work Begins - photo 2

MAHINDRA Projects

MAHINDRA LIFESPACES MURUD
Upcoming

MAHINDRA LIFESPACES MURUD

Murud, Raigad (near Alibaug)

2, 3 BHK • Price on Request

Upcoming coastal homes near Murud-Janjira Fort

MAHINDRA LIFESPACES PANVEL
Upcoming

MAHINDRA LIFESPACES PANVEL

Panvel, Mumbai

1, 2, 3 BHK • Price on Request

Upcoming Mahindra homes near NMIA

Mahindra Lifespaces Thane
Upcoming

Mahindra Lifespaces Thane

Thane, Mumbai

2, 3 BHK • Price on Request

Upcoming Mahindra address in Thane

MAHINDRA ORIGINS BY MAHINDRA CHENNAI PHASE 2B
Upcoming

MAHINDRA ORIGINS BY MAHINDRA CHENNAI PHASE 2B

Eliambedu, Chennai

Industrial & Commercial Plots • Price on request

95-acre industrial expansion on NH-16

Mahindra SEZ Jaipur
Upcoming

Mahindra SEZ Jaipur

Ajmer Road, Jaipur

Commercial Plots • Rs 60 Lakhs onwards

3000-acre Mahindra World City SEZ

Mahindra World City Dholera
Upcoming

Mahindra World City Dholera

Dholera SIR, Ahmedabad

Industrial, Commercial, Residential • Price on Request

Rs 2,000 Cr integrated business city on DMIC

MAHINDRA ALEMBIC
Pre-Launch

MAHINDRA ALEMBIC

Hope Farm, Whitefield, Bangalore

2, 3 BHK • Rs 1.43 Cr onwards*

Pre-launch homes near Hope Farm Metro

Mahindra Chembur Redevelopment
Pre-Launch

Mahindra Chembur Redevelopment

Chembur, Mumbai

2, 3 BHK • Price on Request

₹1,700 Cr redevelopment at Diamond Garden

Get In Touch

Request a Callback

Back

Questions, Answered

What exactly is the Goregaon-Mulund Link Road (GMLR)?
It is a 12.2 km east-west corridor being built by the BMC to connect Goregaon in the western suburbs to Mulund in the eastern suburbs, comprising flyovers, twin tunnels under Sanjay Gandhi National Park, and interchanges at an estimated cost of Rs 14,000 crore.
When will the first GMLR flyover open?
The Goregaon-side flyover between Dindoshi Court and Dadasaheb Phalke Chitranagari was targeted for May 2026, though contractor delays and a penalty on the builder pushed portions of the opening timeline further out through 2026.
When will the GMLR tunnels be ready?
The twin tunnels under Sanjay Gandhi National Park are now officially targeted for completion by October 2028, with the entire GMLR project expected to be fully operational by December 2028.
How much will GMLR reduce travel time between Goregaon and Mulund?
Peak-hour travel currently takes up to 90 minutes; once GMLR is fully operational, this is expected to fall to around 25 minutes, a reduction of roughly 65 minutes each way.
Why has the GMLR project timeline slipped from the original 2026 target?
Utility clearances, land encroachments, and contractor delays on the flyover package pushed the schedule back, while the tunnel package involves boring through basalt rock at depths of up to 143 metres, a technically complex undertaking that has extended the timeline to 2028.
What tunnel boring machines are being used for GMLR?
Two 14.42-metre diameter Rock EPBM tunnel boring machines, among the largest ever deployed in India, are being used to excavate the twin tunnels, each in a single continuous pass of roughly 5.3 km.
How does GMLR progress affect property prices nearby?
Infrastructure corridors in Mumbai typically see price appreciation in phases — a rise when construction visibly progresses, and a further jump on completion. Localities like Goregaon West, Bhandup, Kanjur and Mulund along the GMLR alignment are already seeing renewed developer and buyer interest.
Are there Mahindra Lifespaces projects near the GMLR corridor?
Yes. Mahindra Lifespaces has launched Mahindra Rainforest on LBS Marg, Kanjur, which highlights its proximity to GMLR, and has also secured a redevelopment project in Mulund West less than a kilometre from the alignment.
Will GMLR connect with other Mumbai infrastructure projects?
Yes, GMLR is planned to eventually link with the Versova-Dahisar Coastal Road, creating a wider connected network between the western suburbs, eastern suburbs, and Thane.
Is it safe to buy property near GMLR before it's fully complete?
Buying before full completion often captures the steepest appreciation, but buyers should factor in the revised 2028 tunnel timeline and track official BMC progress updates before committing, especially for possession-linked decisions.

This site is published for general information only and is not an offer or contract. Prices, plans, and specifications are indicative and may change without notice. Buyers should verify all details independently before deciding. About · Projects